13

Semaphore Bridge

Refurbishment of a historic steel bridge supported by cylindrical piles, including structural steel repairs, bearing replacements, and installation of a new deck finish and balustrade. The project upgraded key components while preserving the bridge’s historic integrity.

  • Complex tidal site
  • HSE Inspected site
  • Key asset restored

Client

Kbs Logo Header Removebg Preview

Location

Portsmouth – Dockyard

Overview

Refurbishment of a historic traffic-way bridge at a local MOD site, delivered as principal contractor. Works included full site mobilisation and structural restoration, application of a new multi-coat marine paint system to all steelwork, installation of a new galvanised structural support deck with GRP finish, new balustrade edge protection, replacement roller pin bearings, and associated structural repairs throughout.

The Challenge

Due to the nature of this project, several challenges were encountered, the most significant being tidal conditions. Rising tides periodically submerged the structure, impacting access and progress and requiring careful planning and coordination to complete the works safely and efficiently.

The late-1890s bridge is supported by two main structural girder beams recessed within the granite wall, bearing on steel roller pins. We were tasked with developing a safe and effective design and method of works to replace the existing roller bearings, while maintaining the structural integrity of the bridge throughout the process.

Solution

These conditions impacted every project milestone, with scaffolding erected using a workboat and, at times, wading access. Once the scaffold was in place, structural repairs and UHP (ultra-high-pressure) water blasting were completed, followed by the application of protective paint systems carefully timed to accommodate rising tides.

To overcome the challenges associated with replacing the bridge’s roller bearings, our design team developed a solution using a stainless steel alternative. Given the condition of the existing bearings, this approach was selected to significantly extend the lifespan of the client’s asset. Installation of the new roller bearings and associated components was complex, but was successfully achieved using hydraulic jacks and temporary support systems, ensuring the works were carried out safely and effectively.

All works were completed within a busy operational environment, requiring careful management of traffic, tidal conditions, and subcontractors on a constrained site with limited access. We are proud of the final outcome and thank KBS Maritime for trusting us with the refurbishment of this historic asset.

Working with MTECH, particularly Martin, has been a very smooth experience. Any questions raised—whether in face-to-face meetings or via email—are always answered promptly and professionally. When site visits to Portico were required, Martin was extremely helpful in arranging gate access and ensuring everyone had the correct security clearance and completed the training video. 

The refurbishment itself was carried out to a high standard, and site visits were always welcomed. The end user is very pleased with the addition of the new hydraulics, which significantly reduces manual handling. Overall, working with MTECH has been an excellent experience. 

KBS Maritime

Get in touch today

Have a project in mind? Get in touch with our team to discuss your requirements and discover how we can deliver safe, efficient, and high-quality solutions.

Get in touch
Ae78fbff5a90abdbbec77439d347b3a1a78c7cd6

Other projects

05

Plymouth CATS

Refurbishment of bespoke Plymouth CAT berthing fenders installed along the dockyard quay wall for Royal Navy vessels. Works included the installation of an in-house designed galvanised clamping system to secure the quay fenders and extend the service life of the supporting timber piles.

Read more
IMG 3316

FSU Spacer Pontoons

Lift out and dry store vessels, carrying out comprehensive refurbishments and re-fit of stainless steel hydraulic pin locking systems. All necessary metalwork completed, and marine-grade paint systems applied throughout to ensure long-lasting performance in harsh environments.

Read more
DCIM100MEDIADJI 0361.JPG

Wightlink Fenders

Manufacture and installation of seven new ship-berthing pile fender units for Wightlink Ferries, delivered as part of a planned maintenance programme at Portsmouth’s busy ferry port. The works were carried out to enhance berth protection, improve operational reliability, and support the safe handling of high-frequency vessel movements.

Read more
06

NMRN Lamination Bay

Designed, manufactured, and installed bespoke structural framework to the client’s specifications, achieving precise tolerances of ±1mm. Works included integration of an overhead gantry system to meet operational requirements.

Read more
20220818 113533

Pile 98

Removal of an existing ship navigation pile in Portsmouth Harbour and installation of a new dolphin piling at a precise location, complete with maintenance access and platform.

Read more
20250819 120115340 IOS

15 Dock Cassion

The 15 Dock Caisson is a vital asset for our client, facilitating safe and reliable access for vehicles, plant equipment, and pedestrians across the dry dock. Our scope of work involved the complete replacement of all surfaces and balustrades, ensuring enhanced safety and durability.

Read more
16 (1)

PRJ Lifting Platform

Bespoke made lifting platform to enable our client to lift various plant and vehicles onto Navy vessel safely and efficiently.

Read more